| Small hole excavated at the house pipe bursting head being assembled for bursting 9 a.m. |
| The hole in the street with the bursting puller being installed 11 a.m. |
| Inspected by a City official, Backfilled, soil compacted, Asphalt preparation at 2 p.m. |
| Street patched, pipe completely replaced all work complete 4 p.m. |
| New tap onto the city mainline, large pipe on the left is the clay city main and the green pipe is the customers new 4" sewer line with a new plastic tap saddle. 12 p.m. |